基于动态约束满足的炼钢连铸重调度算法
引用本文:侯东亮,李铁克.基于动态约束满足的炼钢连铸重调度算法[J].计算机应用,2012,32(12):3553-3557.
作者姓名:侯东亮  李铁克
作者单位:1. 北京科技大学 东凌经济管理学院,北京 1000832. 北京科技大学 钢铁生产制造执行系统技术教育部工程研究中心, 北京 1000833. 广东海洋大学 工程学院,广东 湛江 524088
基金项目:教育部博士学科点专项科研基金资助项目(20100006110006);中央高校基本科研业务费专项资金资助项目(FRF-AS-AA-013B)
摘    要:针对转炉出钢延迟的炼钢连铸重调度问题,以开工时间、加工时间以及加工机器的差异度和同一炉次相邻设备间的等待时间的差异化最小为目标建立了动态约束满足模型,提出了基于约束满足和断浇修复的重调度算法。算法通过变量和值选择规则依次对变量赋值,利用冲突识别与解消规则识别赋值过程中产生的冲突并予以解消冲突;在形成的准可行调度中,利用断浇修复启发式规则修复连铸机的断浇现象。仿真实验模拟了3组均匀分布随机产生的延迟时间量,所得目标值分别为0.15,0.28和0.51。结果表明延迟时间量的大小对目标函数值有一定影响,所提算法能够最大限度地满足生产的实时性和稳定性的需求。

关 键 词:调度修复  动态约束满足  重调度  炼钢连铸  
收稿时间:2012-07-17
修稿时间:2012-08-27

Rescheduling algorithm for steelmaking and continuous casting based on dynamic constraint satisfaction
HOU Dong-liang,LI Tie-ke.Rescheduling algorithm for steelmaking and continuous casting based on dynamic constraint satisfaction[J].journal of Computer Applications,2012,32(12):3553-3557.
Authors:HOU Dong-liang  LI Tie-ke
Affiliation:1. Dongling School of Economics and Management, University of Science and Technology Beijing, Beijing 100083, China2. Engineering Research Center of Manufacturing Execudon System Technology for Iron and Steel Production, Ministry of Education, University of Science and Technology Beijing, Beijing 100083, China3. Faculty of Engineering, Guangdong Ocean University, Zhanjiang Guangdong 524088, China
Abstract:A rescheduling problem of steelmaking-continuous casting with tapping tardiness was studied in this paper. And a dynamic constraint satisfaction model was established to minimize the difference of the starting time, processing time and processing machine and waiting time of the heat between the adjacent equipment. According to this model, a local repair algorithm based on dynamic constraint satisfaction techniques and interrupted-cast repair rules was put forward. In this method, variable selection and value selection rules were used to assign one value to a variable. The conflict identification and elimination principles were used to identify and eliminate the conflicts in the assignment. The interrupted-cast repair heuristic rule was used to repair the interrupted-casts in a continuous casting machine. In this experiment, three groups of random data with a uniform distribution were generated. Target values were 0.15, 0.28 and 0.51. The results demonstrate that the size of the delay time has a certain influence on target value and the algorithm can satisfy the needs of real-time and stability as much as possible.
Keywords:schedule repair                                                                                                                          dynamic constraint satisfaction                                                                                                                          rescheduling                                                                                                                          steelmaking and continuous casting