宝钢工程钢管桩在地基土中25年的腐蚀
引用本文:张桐庆. 宝钢工程钢管桩在地基土中25年的腐蚀[J]. 宝钢技术, 2004, 0(5): 1-4,60
作者姓名:张桐庆
作者单位:宝钢股份公司,设计管理处,上海,201900
摘    要:宝钢一期工程使用的钢管桩打入地下已25年,桩身腐蚀关系其使用寿命及宝钢的安全.文章通过设计使用及实测分析认为防腐蚀设计是安全的,并为管壁腐蚀厚度取值提供了实践依据.

关 键 词:钢管桩  腐蚀  管壁腐蚀厚度设计
文章编号:1008-0716(2004)05-0001-04

Corrosion Condition of Steel Piles Used in Baosteel Project for 25 Years
ZHANG Tong-qing. Corrosion Condition of Steel Piles Used in Baosteel Project for 25 Years[J]. Baosteel Technology, 2004, 0(5): 1-4,60
Authors:ZHANG Tong-qing
Abstract:Steel piles used in Baosteel Phase One Project have been driven into ground for 25 years. The corrosion condition of these piles would influence Baosteel structures safety and duration. This article testifies that the anticorrosion design for Baosteel Project is safe through analyzing the steel pile's condi tion . It also provides the thickness value for tube wall on the basis of the practical evidence.
Keywords:Steel pile  Corrosion J Anticorrosion thickness design for tubes