干燥粉细砂隧道超前预加固与施工研究
引用本文:朱正国,孙星亮. 干燥粉细砂隧道超前预加固与施工研究[J]. 岩石力学与工程学报, 2013, 32(9): 1909-1916
作者姓名:朱正国  孙星亮
作者单位:(1. 石家庄铁道大学 土木工程学院,河北 石家庄 050043;2. 石家庄铁道大学 道路与铁道工程安全保障省部共建教育部重点实验室,河北 石家庄 050043)
基金项目:国家自然科学基金资助项目(51078243);河北省自然基金资助项目
摘    要: 大西铁路客运专线上白隧道穿越干燥粉细砂地层,施工难度及风险很大。通过现场密排小导管和深层咬合桩预加固效果对比试验,得出深层咬合桩预加固可有效控制开挖中的流砂及涌砂。同时,对粉细砂地层及深层咬合桩固结体进行直剪试验、三轴试验及侧限压缩试验等室内试验,得到地层及固结体的各项物理力学指标,且认为三轴试验所得各指标更为真实、可靠。在此基础上,对干燥粉细砂地层隧道开挖方法进行数值模拟和现场试验测试,提出合理的施工方法建议。研究结果为上白隧道施工提供技术支持,也可供类似工程参考。

关 键 词:隧道工程干燥粉细砂地层预加固施工
收稿时间:2012-12-25

PRE-REINFORCEMENT AND CONSTRUCTION OF TUNNEL IN DRY FINE SAND LAYERS
ZHU Zhengguo , SUN Xingliang. PRE-REINFORCEMENT AND CONSTRUCTION OF TUNNEL IN DRY FINE SAND LAYERS[J]. Chinese Journal of Rock Mechanics and Engineering, 2013, 32(9): 1909-1916
Authors:ZHU Zhengguo    SUN Xingliang
Affiliation:(1. School of Civil Engineering,Shijiazhuang Tiedao University,Shijiazhuang,Hebei 050043,China;;2. Key Laboratory of Roads and Railway Engineering Safety Control of Ministry of Education,Shijiazhuang Tiedao University,Shijiazhuang,Hebei 050043,China)
Abstract:Shangbai large cross-section tunnel in Datong-Xi?an Passenger Dedicated Lines passes through dry fine sand layers. Its construction technologies are difficult and risky. Through the comparative field experiments of close-packed small pipe and deep secant pile of pre-reinforcement,it is found that the deep secant pile pre-reinforcement scheme can effectively control the quick sand and sand gushing during the tunnel excavation. Meanwhile the physico-mechanical parameters of the fine sand layers and consolidation body are obtained by deep secant pile test through laboratory tests,including direct shear tests,triaxial tests and unconfined compression tests. On this basis,through the numerical simulation and field test of tunnel excavation method in dry fine sand layers,the reasonable construction scheme is proposed. The results can provide technical support for Shangbai tunnel construction and reference for similar projects.
Keywords:tunnelling engineering  dry fine sand layers  pre-reinforcement  construction