毛尔盖心墙堆石坝防渗墙与坝体防渗体连接形式
引用本文:田景元,王平,刘汉龙,张鹏飞.毛尔盖心墙堆石坝防渗墙与坝体防渗体连接形式[J].水利水电科技进展,2010,30(4):41-45.
作者姓名:田景元  王平  刘汉龙  张鹏飞
作者单位:1. 中国水电顾问集团成都勘测设计研究院,四川,成都,610072
2. 河海大学岩土工程研究所,江苏,南京,210098
3. 中国水电顾问集团成都勘测设计研究院,四川,成都,610072;河海大学水利水电学院,江苏,南京,210098
基金项目:国家自然科学基金委员会、二滩水电开发有限责任公司雅砻江水电开发联合研究基金 
摘    要:介绍毛尔盖心墙堆石坝概况:最大坝高为147 m,河床覆盖层厚度为30~50 m,拟用混凝土防渗墙对坝基进行防渗处理。在分析防渗墙与心墙防渗体各种连接形式的优缺点之后,结合本工程实际和工程经验,选定防渗墙按硬接头接廊道的连接形式。进行有限元计算分析,确定防渗结构参数,防渗墙仅取1道,墙厚1.4 m。实践表明,采用该方案防渗墙和廊道内的应力适中、投资较少。

关 键 词:心墙堆石坝  深厚覆盖层  混凝土防渗墙  混凝土廊道  防渗体连接形式  毛尔盖水电站大坝
修稿时间:2010/9/2 0:00:00

Joint types for impervious walls and core mass of Maoergai core wall rockfill dam
TIAN Jing-yuan,WANG Ping,LIU Han-long,ZHANG Peng-fei.Joint types for impervious walls and core mass of Maoergai core wall rockfill dam[J].Advances in Science and Technology of Water Resources,2010,30(4):41-45.
Authors:TIAN Jing-yuan  WANG Ping  LIU Han-long  ZHANG Peng-fei
Abstract:Maoergai core wall rockfill dam has the maximum height of 147 m and the overburden layer is 30~50 m in thickness.The dam foundation will be treated by use of impervious walls of concrete.The advantages and disadvantages of the joint types for impervious walls and core mass were analyzed.Based on the engineering background and experience,the scheme of gallery type with rigidity mode for the impervious walls was selected.FEM calculation and analyzed were employed to determine parameters for impervious structure,and only one impervious wall 1.4 m in thickness was adopted for Maoergai core wall rockfill dam.The case practice shows that the proposed scheme results in the moderate stress situation in the gallery and the concrete walls and relatively smaller engineering investment.
Keywords:core wall rockfill dam  thick overburden layer  concrete anti-seepage wall  concrete gallery  joint type  Maoergai Hydropower Station