首页 | 本学科首页   官方微博 | 高级检索  
     

百色水利枢纽大坝混凝土浇筑方法研究
引用本文:蒙承刚. 百色水利枢纽大坝混凝土浇筑方法研究[J]. 广西水利水电, 1999, 0(4): 42-46
作者姓名:蒙承刚
作者单位:广西水利电力勘测设计研究院,南宁,530023
摘    要:大坝混凝土施工是百色水利枢纽主体工程施工的关键,施工时间短,工程量相对较大。大坝混凝土总方量247.53 万m3 ,其中辗压混凝土(RCC)190 .79 万m3 。经比较,RCC运输采用深槽高速皮带机辅以负压真空溜筒的入仓方式。

关 键 词:浇筑方法  碾压混凝土  百色水利枢纽

Study of the main dam concrete placing method of the Baise WRPP
Meng Chenggang. Study of the main dam concrete placing method of the Baise WRPP[J]. Gx Water Resources & Hydropower Engineering, 1999, 0(4): 42-46
Authors:Meng Chenggang
Abstract:The main dam concrete construction is the key of the Baise WRPP main body project construction. Its working term is shorter and the construction quantity is larger.The total quantity of the main dam concrete placing is 247.53*10 4 m 3,among which,RCC is 190.79*10 4 m 3.Through comparation,the RCC transmission use the format of deep channel quick conveyor combining with nagative pressure vacuum elephant trunk.
Keywords:placing method  rolled concrete  the Baise WRPP