首页 | 本学科首页   官方微博 | 高级检索  
     

恒源矿深井大断面岩巷快速掘进技术的研究与应用
引用本文:马力,牛志军,姚强岭.恒源矿深井大断面岩巷快速掘进技术的研究与应用[J].中国矿业,2020,29(3).
作者姓名:马力  牛志军  姚强岭
作者单位:皖北煤电集团公司 生产技术部,中国矿业大学 煤炭资源与安全开采国家重点实验室,中国矿业大学 煤炭资源与安全开采国家重点实验室
基金项目:国家自然科学基金资助项目(51874283);江苏省自然科学基金面上资助项目(BK20161184)
摘    要:为了解决恒源煤矿深部大断面岩巷因高地应力以及矿井灾害多等导致的巷道进尺较慢的问题,本文通过对-960m水平东翼轨道大巷原有掘进技术进行分析,得到影响掘进速度的因素为地质条件客观因素和装备人员主观因素,然后通过对新型掘进技术的调研并结合大巷的地质条件,引进了"CMJ2-30液压掘进钻车+ZWY-180/79L型挖掘装载机+ST-8/6B型梭车"机械化作业线,使用了中深孔光面爆破技术并加强了劳动组织管理,炮眼利用率提高到80%左右,日进尺由1.6m提升至2.8m,并在2018年9月~12月期间共进尺354m,平均月进尺88.5m,较大程度地加快了大巷掘进速度,有效缓解了该矿采掘失衡的问题。

关 键 词:岩巷  深井大断面  钻爆法  中深孔爆破  劳动组织管理
收稿时间:2019/7/24 0:00:00
修稿时间:2020/3/10 0:00:00

Research and Application of Rapid excavation Technology for large Section Rock roadway in Deep well of Hengyuan Mine
MA Li,NIU Zhijun and YAO Qiangling.Research and Application of Rapid excavation Technology for large Section Rock roadway in Deep well of Hengyuan Mine[J].China Mining Magazine,2020,29(3).
Authors:MA Li  NIU Zhijun and YAO Qiangling
Affiliation:Ministry of production Technology,Northern Anhui Coal and Power Group Co,Ltd,Suzhou,Key Laboratory of Deep Coal Resource Mining,Ministry of Education of China,China University of Mining and Technology,Xuzhou,Key Laboratory of Deep Coal Resource Mining,Ministry of Education of China,China University of Mining and Technology,Xuzhou
Abstract:The shallow coal resources of Hengyuan Coal Mine are nearly finished. In order to prolong the service life of the mine and increase the recovery rate of coal resources in China, the mine decided to mine deep coal resources in the mining area. Hengyuan Coal Mine is currently excavating - 960m horizontal East Wing track roadway, which is facing problems of high ground stress and many mine disasters. The mechanized working line of "YT28 gas leg rock drill + P120B rake bucket rock loader + mine truck" was initially adopted in the main roadway. There are some problems such as slow drilling speed and low rock loading efficiency, which seriously affect the mining replacement balance. Based on the investigation of the excavation technology of large cross-section rock roadway in deep mine and the geological conditions of the roadway, this paper introduces the mechanized operation line of "CMJ2-30 hydraulic excavation drilling rig + ZWY-180/79L excavation loader + shuttle truck", uses medium and deep hole smooth blasting technology and strengthens the management of labor organization. The utilization ratio of blasting hole is increased to about 80% and the daily advance ruler is increased. From 1.6m to 2.8m, and in the four months from September to December 2018, a total of 354m, with an average monthly advance of 88.5m, has greatly accelerated the speed of roadway excavation and effectively alleviated the problem of mining imbalance in this mine.
Keywords:rock roadway  Deep well with large section  drilling and  blasting method  medium and deep hole blasting  labor organization management