龙滩水电站机组座环整体吊装
引用本文:袁训国. 龙滩水电站机组座环整体吊装[J]. 水力发电, 2007, 33(4): 46-48
作者姓名:袁训国
作者单位:中国水利水电第七工程局机电安装分局,四川,彭山,620860
摘    要:介绍了龙滩水电站水轮机座环组装后的整体吊装情况及方案选择,并对各吊具进行了计算较核,保证了座环吊装安全,减少了吊装工器具投入,同时也节省了时间,可为水电站厂房内大件吊装特别是带有蜗壳末端,大舌板的偏重座环吊装提供经验。

关 键 词:机组座环  整体吊装  偏重  龙滩水电站
文章编号:0559-9342(2007)04-0046-03
修稿时间:2007-03-20

Integral Lifting of the Stay Ring for the Generating Unit of Longtan Hydropower Station
Yuan Xunguo. Integral Lifting of the Stay Ring for the Generating Unit of Longtan Hydropower Station[J]. Water Power, 2007, 33(4): 46-48
Authors:Yuan Xunguo
Abstract:This paper introduces the integral lifting and alternative selection after the stay ring of turbine for Longtan Hydropower Station was assembled. The detailed calculation and recheck were conducted for the various lifting devices in order to ensure the safety of lifting.It not only reduced the boisting equipment but also saved time,which can provide the experience for the lifting of big equipment,especially for the lifting of the end of spiral case and the stay ring in the powerhouse of hydropower station.
Keywords:stay ring   integral lifting   emphasis   Longtan Hydropower Station