滨海核电厂地基处理方法综述
引用本文:罗朝专. 滨海核电厂地基处理方法综述[J]. 工程建设与设计, 2010, 0(9): 99-102
作者姓名:罗朝专
作者单位:深圳中广核工程设计有限公司,广东,深圳,518031
摘    要:滨海核电厂的建设场地通常需进行开挖山体、填海造陆。通过对海底淤泥处理、场地推填、夯实、局部特殊区域处理的介绍,结合宁德核电厂的具体应用实例对适用于滨海核电厂的地基处理方案进行了总结,为同类工程提供借鉴。

关 键 词:滨海核电  开山填海  地基处理

Application of Ground Treatment of Coastal Nuclear Power Plant
LUO Chao-zhuan. Application of Ground Treatment of Coastal Nuclear Power Plant[J]. Construction & Design for Project, 2010, 0(9): 99-102
Authors:LUO Chao-zhuan
Affiliation:LUO Chao-zhuan (China Nuclear Power De sign Company.,LTD., Shenzhen 518031, China)
Abstract:The construction ground for nuclear power plant on coastal region are usually formed by excavating hill and filling offshore. Through introduction of the treatment of seabed mud, offshore filling, compaction,and treatment in special area. Combined with the application cases of Ningde Nuclear Power Plant, the common ground treatment applied to coastal nuclear powerplant are summarized. The results can be used as reference for other similar projects.
Keywords:coastal nuclear power plant  excavating hill and filling offshore  ground treatment