利用后部高抽放巷治理综放工作面初采期瓦斯 |
| |
引用本文: | 任晓峰,周建斌,任发伍. 利用后部高抽放巷治理综放工作面初采期瓦斯[J]. 煤炭科学技术, 2001, 29(5): 4-7 |
| |
作者姓名: | 任晓峰 周建斌 任发伍 |
| |
作者单位: | 阳泉煤业(集团)有限责任公司 五矿, |
| |
摘 要: | 分析了阳泉煤业 (集团 )有限责任公司五矿 15煤综放工作面初采期瓦斯超限原因 ,提出了利用低位及中低位后部高抽放巷解决初采瓦斯试验方案 ,通过试验取得成功 ,确保了综放工作面初采安全顺利推进
|
关 键 词: | 后部高抽巷 初采期 瓦斯治理 |
文章编号: | 0253-2336(2001)05-0004-04 |
修稿时间: | 2000-10-10 |
Rear High Level GasDrainage Gateway Applied to Control Gas from Initial Coal Mining of Fully MechanizedMining Face |
| |
Abstract: | A mining method in No.5 Mine of Yangquan Mining Group Corp. is a fully mechanized one pass cut caving method. Above the No.15 mining seam, there is a unmined protective seam. The No.15 seam is a spontaneous combustion seam. A gas drainage operation in the tailgate and inclined high level drainage gateway was not suitable to be applied to control the gas problem occurred in the mining period. A high level gas drainage gateway along the seam roof strike applied to gas control was shown that the gas drainage along the roof strike had a high gas drainage volume, high drainage efficiency, a good continuous drainage operation and other features. But at the initial period, due to the falling depth of the roof and the cracks in the roof not reached to the strike high level gas drainage seam, the drainage result did not reach an expected result. With series measures, unfavorable factors overcame at the initial mining period have basically solved the gas content over limit at mining face at the initial mining period. |
| |
Keywords: | |