蒲石河抽水蓄能电站上水库库周帷幕灌浆施工
引用本文:罗爱民,王明锐. 蒲石河抽水蓄能电站上水库库周帷幕灌浆施工[J]. 水力发电, 2011, 37(7)
作者姓名:罗爱民  王明锐
作者单位:中国人民武装警察部队水电第一总队第一支队,河北唐山,063004
摘    要:蒲石河抽水蓄能电站上水库库周帷幕轴线长1 618.6 m.设计帷幕灌浆为单排孔,孔距2.0 m,帷幕深入基岩相对不透水层以下3.0 m,钻孔深55.7~99.9 m.帷幕灌浆采取自下而上分段卡塞、孔内循环式灌浆法;对岩石节理发育、破碎及无法实现自下而上分段灌浆的不良部位,采用自上而下分段孔口封闭灌浆法施工.对全部帷幕灌浆孔进行孔斜测量,孔底偏差均满足设计要求.

关 键 词:库周防渗  帷幕灌浆  蒲石河抽水蓄能电站

Curtain Grouting for the Upper Reservoir of Pushihe Pumped-storage Power Station
Luo Aimin,Wang Mingrui. Curtain Grouting for the Upper Reservoir of Pushihe Pumped-storage Power Station[J]. Water Power, 2011, 37(7)
Authors:Luo Aimin  Wang Mingrui
Affiliation:Luo Aimin,Wang Mingrui(The 1st Detachment of 1st General Contingent of Chinese People's Armed Police Hydropower Troops,Tangshan 063004,Hebei,China)
Abstract:The axis of curtain grouting surrounding the upper reservoir of Pushihe Pumped-storage Power Station is 1 618.6 m long.The curtain grouting holes is designed as a single row with a hole distance of 2.0 m.The curtain will deep into the relative impermeable rock about 3 m,so the depth of holes is about 55.7 ~ 99.9 m.The stage and circulation grouting is conducted from bottom to top,but for the holes in joint-developed and broken rocks,the stage grouting is conducted from top to bottom.The inclinations of all ...
Keywords:seepage control surrounding reservoir  curtain grouting  Pushihe Pumped-storage Power Station  