白山抽水蓄能电站输水系统设计
引用本文:刘秀梅,姜宏军,高占坤. 白山抽水蓄能电站输水系统设计[J]. 东北水利水电, 2009, 27(6): 1-3
作者姓名:刘秀梅  姜宏军  高占坤
作者单位:黑龙江肇州县城建处,黑龙江,肇州,166400;华东勘测设计研究院,浙江,杭州,310014;黑龙江省水利科学研究院,黑龙江,哈尔滨,150000
摘    要:白山水电站的扩建项目,其输水系统的布置经方案比较,采用引水洞两机两洞,地下式厂房;尾水洞为两机一洞布置,两个进水口布置在二期厂房与白山水库泄洪洞冲坑之间的左崖山体处;出水口布置在大坝左肩上游约120m处。其设计经论证比较在技术上是可行的,经济上是合理的。

关 键 词:输水系统  布置  白山抽水蓄能电站

Design of water conveyance system for Baishan pumped storage power station
LIU Xiu-mei,JIANG Hong-jun,GAO Zhao-kun. Design of water conveyance system for Baishan pumped storage power station[J]. Water Resources & Hydropower of Northeast China, 2009, 27(6): 1-3
Authors:LIU Xiu-mei  JIANG Hong-jun  GAO Zhao-kun
Abstract:Based on the scheme comparison,the layout of water conveyance system is determined in the extension project of Baishan pumped storage power station.In this layout,the diversion tunnel adopts the twomachine,the two-tunnel and underground power house,and the tailrace tunnel adopts the two-machine and one-tunnel.The two intakes are layout at the left of mountain body between the second stage powerhouse and spillway tunnel scour pool of Baishan reservoir,and the outlet is layout at the upper reaches about 120m ...
Keywords:water conveyance system  layout  Baishan pumped storage power station  