三峡水轮发电机组最大容量和设临时转轮问题
引用本文:商轲,黄奋杰,青长庚,吴次光. 三峡水轮发电机组最大容量和设临时转轮问题[J]. 云南水力发电, 1996, 0(3)
作者姓名:商轲  黄奋杰  青长庚  吴次光
作者单位:鲁布革水电科技实业公司,电力部昆明勘测设计院
摘    要:三峡机组运行水头变幅大,为避免高水头小开度运行出现不稳定问题,宜设置最大容量.三峡水库因施工和移民安排分期蓄水,为使在较低水位的运行初期获得更多的经济效益,宜在最早投运的一批机组设置临时转轮.

关 键 词:三峡机组,稳定运行,最大容量,临时转轮

Problems on the maximum Capacity of Three Gorges Turbine Generating Sets and Runners Installed Temporarily
Shang Ge,Huang Fenjie. Problems on the maximum Capacity of Three Gorges Turbine Generating Sets and Runners Installed Temporarily[J]. Yunnan Water Power, 1996, 0(3)
Authors:Shang Ge  Huang Fenjie
Abstract:Since the operating head of Three Gorges generating sets have large variable amplitude,it is better to provide the generating sets with maximum capacity to avoid arising unsteady state while they are operating under high head and small apertures. Filling of Three Gorges reservoir has to be arranged by stages because of construction and resettling the migrations,so it is suitable to provide termporary runners for some generating sets in the early stage to increase more economic benefits at lower water levels during the initial operating period.
Keywords:Three Gorges generating set   steady operation   maximum capacity  temporary runner