基于ANSYS的陕北换流站直流接地极地电位分布计算
引用本文:马成廉,王乐天,李波,李颖瑾,郝洪震,赵书健,国敢. 基于ANSYS的陕北换流站直流接地极地电位分布计算[J]. 中国电力, 2018, 51(5): 52-60. DOI: 10.11930/j.issn.1004-9649.201711169
作者姓名:马成廉  王乐天  李波  李颖瑾  郝洪震  赵书健  国敢
作者单位:1. 东北电力大学 输变电技术学院, 吉林 吉林 132012;2. 山东电力工程咨询院有限公司, 山东 济南 250013
基金项目:国家自然科学基金资助项目(51577060,51677068)。
摘    要:在特高压直流输电(UHVDC)工程规划设计阶段需要进行地表电位的分布计算,参考了陕北换流站工程中府谷大柳树墕村接地极大地电磁测深(MT)法实测的大地分层电阻率数据,建立了6层大地土壤分层模型,并应用ANSYS计算了在额定运行工况下接地极方圆100km范围内的大地电位分布。结果表明,接地极方圆2km范围内地电位下降迅速,不应规划建设电力、通信、铁道及管道等设施。所得陕北换流站地区已建及远景规划的各变电站及电厂的地电位分布结果,可对陕湖特高压直流输电工程单极运行调试提供参考。

关 键 词:UHVDC  直流接地极  ANSYS  仿真计算  地面电位分布  
收稿时间:2017-11-23
修稿时间:2017-12-20

Simulation Study on the DC Grounding Electrode Earth Potential Distribution of Northern Shaanxi Converter Station Based on ANSYS
MA Chenglian,WANG Letian,LI Bo,LI Yingjin,HAO Hongzhen,ZHAO Shujian,GUO Gan. Simulation Study on the DC Grounding Electrode Earth Potential Distribution of Northern Shaanxi Converter Station Based on ANSYS[J]. Electric Power, 2018, 51(5): 52-60. DOI: 10.11930/j.issn.1004-9649.201711169
Authors:MA Chenglian  WANG Letian  LI Bo  LI Yingjin  HAO Hongzhen  ZHAO Shujian  GUO Gan
Affiliation:1. Technological School of Transmission and Transformation, Northeast Electric Power University, Jilin 132012, China;2. Shandong Electric Power Engineering Consulting Institute Co., Ltd., Jinan 250013, China
Abstract:The distribution of earth surface potential needs to be calculated in UHVDC engineering planning and design. Based on the stratified earth resistivity data measured by magnetotelluric sounding method (MT method) from one China converter station project located in Daliushu Yan Village, Fugu County of Northern Shaanxi, a 6-layer earth soil stratification model is established. The potential distribution in the range of 100 km around the grounding electrode is analyzed by ANSYS under rated operating condition. The results show that the electric potential decreases rapidly in the range of 2 km around the DC grounding electrode, where the facilities of electric power, communications, railways and pipelines shall not be planned and built. The earth surface potential distribution of the built and planned substations and power plants in the area around the Northern Shaanxi converter station has been calculated, and the results can be used as a reference for the single pole operation debugging of Northern Shaanxi-Hubei UHVDC transmission project.
Keywords:UHVDC  DC grounding electrode  ANSYS  simulation &calculation  earth surface potential distribution  