200 kV变电所母线安装技术问题分析与处理
引用本文:刘宇峰. 200 kV变电所母线安装技术问题分析与处理[J]. 黑龙江电力, 2007, 29(2): 134-135,151
作者姓名:刘宇峰
作者单位:黑龙江省火电第一工程公司,黑龙江,哈尔滨,150090
摘    要:针对哈尔滨第三发电厂220 kV变电所接线方式的特点,从分析导体膨胀、大电流导体连接等电缆安装的问题人手,计算母线安装下料长度,阐明母线安装施工工艺.

关 键 词:设备安装  变电所  导线
文章编号:1002-1663(2007)02-0134-02
修稿时间:2007-02-06

Bus line installation technique analysis and handling for 220 kV substation
LIU Yufeng. Bus line installation technique analysis and handling for 220 kV substation[J]. Heilongjiang Electric Power, 2007, 29(2): 134-135,151
Authors:LIU Yufeng
Affiliation:Heilongjiang Thermal Power No. 1 Engineering Company, Harbin 150090, China
Abstract:The bus line cutting length while installation was calculated, and discussed its iustallation procedure, focusing on the features of 220 kV substation wiring way and in view of solving conductor expansion, connection of high current conductor,and cable installation.
Keywords:equipment installation    substation    wiring