地下连续墙施工重难点分析与应对措施
引用本文:周建龙. 地下连续墙施工重难点分析与应对措施[J]. 山西建筑, 2012, 38(1): 84-85
作者姓名:周建龙
作者单位:天津市地下铁道集团有限公司,天津,300000
摘    要:对地下连续墙的分类以及优缺点进行了总结,分析了地下连续墙的施工难点,提出了各施工难点的应对措施,以期不断完善地下连续墙施工工艺,进而推广其在基坑工程中的应用。

关 键 词:地下连续墙  施工难点  应对措施

On analysis of difficult and key points of underground continuous walls construction and respective measures
ZHOU Jian-long. On analysis of difficult and key points of underground continuous walls construction and respective measures[J]. Shanxi Architecture, 2012, 38(1): 84-85
Authors:ZHOU Jian-long
Affiliation:ZHOU Jian-long
Abstract:The paper sums up the classification of underground continuous walls and their advantages and disadvantages,analyzes the construction difficulties of the underground continuous walls,and points out the respective measures for the construction difficulties,so as to improve the construction craft of the underground continuous walls and to extend its application in foundation pit projects.
Keywords:underground continuous walls  construction difficulties  respective measures