首页 | 本学科首页   官方微博 | 高级检索  
     

方山资源综合利用电厂的改造
引用本文:刘旺兴. 方山资源综合利用电厂的改造[J]. 煤炭加工与综合利用, 2009, 0(3): 42-45
作者姓名:刘旺兴
作者单位:霍州煤电集团有限责任公司,山西,霍州,031400
摘    要:介绍了方山资源综合利用电厂运行现状;为了充分利用煤矸石、煤泥等劣质燃料,同时满足当地供热需求,方山电厂要对3#机组进行技术改造;探讨了技改的装机方案、机组选型、接入系统方案及投资额等内容。

关 键 词:资源综合利用  电厂  煤泥  煤矸石  热电联产  改造

Conversion of Fangshan Power Plant constructed for comprehensive utilization of resources
LIU Wang-xing. Conversion of Fangshan Power Plant constructed for comprehensive utilization of resources[J]. Coal Processing & Comprehensive Utilization, 2009, 0(3): 42-45
Authors:LIU Wang-xing
Affiliation:Shanxi Huozhou Coal & Elec.Group Co.;Ltd.;Huozhou;Shanxi 031400;China
Abstract:Present status of Fangshan Power Plant constructed for comprehensive utilization of resources introduced;for complete utilization of inferior fuel as coal refuse and sludge and simultaneously satisfying local need of thermal heating,the #3 generator set was technically converted;which work included options of technical conversion,selection of generator set,option of connecting system and amount of investment estimated.
Keywords:comprehensive utilization of resources  power plant  coal sludge  coal refuse  co-production of heat and electricity  conversion  