首页 | 本学科首页   官方微博 | 高级检索  
     

棉花滩水电站机电设备的调试
引用本文:林祖建,林其煌.棉花滩水电站机电设备的调试[J].水力发电,2003,29(11):48-50.
作者姓名:林祖建  林其煌
作者单位:福建省电力试验研究院,福建,福州,350007
摘    要:棉花滩水电站是全国电力系统第一个整体达标投产的水电工程,也是率先将机电设备安装与调试分开,引进专业调试队伍承接机电设备调试的单位。调试单位加强与相关参建单位问协调配合的做法以及在调整试验中加强安全管理及质量管理的经验,可供其他工程项目参考。

关 键 词:调试  机电设备  安全管理  质量管理  棉花滩水电站
文章编号:0559-9342(2003)11-0048-03
修稿时间:2003年4月24日

The commissioning of electrical and mechanical equipment at Mianhuatan Hydropower Station
Abstract:The Mianhuatan hydropower station is the first hydropower engineering which was up to scratch in its entirety,and also is the first hydropower engineering which introduced professional commissioning teams. The construction and commissioning of electrical and mechanical equipment were carried out separately. This paper introduces the methods of commissioning teams enhancing the cooperation with construction teams and its experience of enhancing the safety and quality management in commissioning, also briefly introduces the situation of commissioning.
Keywords:commissioning  electrical and mechanical equipment  safety management  quality control  coordination Mianhuatan Hydropower Station
本文献已被 CNKI 维普 万方数据 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号