240m高钢筋混凝土烟囱爆破拆除及振动控制技术
作者单位:;1.河南理工大学土木工程学院;2.河南迅达爆破有限公司
摘    要:针对复杂环境下240m高钢筋混凝土烟囱定向爆破拆除项目,通过采用延时爆破技术、开挖减振沟和铺设黄土缓冲垫层等一系列防护措施对振动进行控制,并对爆破振动进行了监测分析,有效控制了爆破振动的影响,减振效果显著,可为同类拆除爆破工程提供参考。

关 键 词:钢筋混凝土烟囱  爆破拆除  防护措施  振动控制

BLASTING DEMOLITION OF A 240M HIGH REINFORCED CONCRETE CHIMNEY AND THE VIBRATION CONTROL TECHNOLOGY
Affiliation:,School of Civil Engineering,Henan Polytechnic University,Henan Schindler Blasting Co.,Ltd.
Abstract:The blasting demolition project of 240m high reinforced concrete chimney in complex environment was introduced.The vibration was controlled through a series of protective measures such as delay blasting technology,digging damping ditches and laying loess cushions.The blasting vibration monitoring data was analyzed also.Affects of blasting vibration were effectively controlled and the effect was significant.It could provide a reference for similar demolition blasting engineerings.
Keywords:Reinforced concrete chimney  Blasting demolition  Protective measures  Vibration control