大型灯泡贯流式水轮机出力不足原因分析与现场测试研究
引用本文:刘忠,黄竹青,饶洪德,焦烨,肖启志,李建勇. 大型灯泡贯流式水轮机出力不足原因分析与现场测试研究[J]. 水利水电技术, 2012, 43(12): 86-88,91
作者姓名:刘忠  黄竹青  饶洪德  焦烨  肖启志  李建勇
作者单位:(1.长沙理工大学“可再生能源电力技术”湖南省普通高等学校重点实验室,湖南长沙410004;2.洪江水电厂,湖南洪江418200)
基金项目:"水力机械过渡过程"教育部重点实验室开放基金项目,五凌电力科技项目
摘    要:洪江水电厂3#灯泡贯流式水轮机自2003年9月份投产以来就一直存在出力不足的状况,经济损失较大。为此,从理论上分析了该水轮机出力和效率的主要影响因素,确定了3#、5#和6#水轮机导叶和桨叶叶型、间距的现场测试方案。测试研究结果表明,3#和6#水轮机的导叶和桨叶叶型分别基本一致,在各桨叶转角下3#水轮机的桨叶间隔平均值普遍小于5#水轮机的相应间距值。

关 键 词:大型灯泡贯流式水轮机  出力不足  现场试验  理论分析  导叶  桨叶  测量  
收稿时间:2012-05-22

Causal analysis and in-situ testing on output deficiency of a large bulb tubular turbine
LIU Zhong , HUANG Zhuqing , RAO Hongde , JIAO Ye , XIAO Qizhi , LI Jianyong. Causal analysis and in-situ testing on output deficiency of a large bulb tubular turbine[J]. Water Resources and Hydropower Engineering, 2012, 43(12): 86-88,91
Authors:LIU Zhong    HUANG Zhuqing    RAO Hongde    JIAO Ye    XIAO Qizhi    LI Jianyong
Affiliation:(1.Key Laboratory of Power Technology of Renewable Energy Resources, Hunan Province, Changsha University of Science and Technology, Changsha410004,Hunan,China; 2.Hongjiang Hydropower Plant, Hongjiang418200, Hunan,China)
Abstract:Since the commissioning in Sept.2003, the No.3 bulb tubular turbine in Hongjiang Hydropower Plant has all along operated under an operation condition of output deficiency, and then the economic loss is larger.Therefore, the main factors of the impacts on the output and efficiency of the turbine are theoretically analyzed herein.Furthermore, a scheme of the in-situ testing on the shapes and spaces of the guide vanes and runner blades of the No.3, No.5 and No.6 turbines therein is determined.The testing result shows that the shapes of the guide vanes and runner blades of the No.3 turbine and No.6 are basically the same respectively, however, mean value of the spaces in between all the runner blades of the No.3 turbine under their twist angles is generally less than those corresponding spaces of the No.5 turbine.
Keywords:large bulb tubular turbine  output deficiency  in-situ testing  theoretical analysis  guide vane;runner blade  measurement  