引用本文:张俊英. 隧洞衬砌全圆针梁台车抗浮结构设计[J]. 水利水电技术, 2012, 43(12): 48-51
作者姓名:张俊英
作者单位:(中铁十三局集团有限公司,天津300308)
摘    要:北京市南水北调配套工程南干渠七标浅埋暗挖隧洞为双线DN3 400 mm输水隧洞,其二次衬砌采用全圆式针梁台车施工。为应对台车在浇筑过程中通常会出现的上浮问题,在该台车设计之初便对抗浮进行了细致计算。实际衬砌浇筑证明,该台车抗浮装置可有效地防止其上浮,为以后类似工程积累相关经验。

关 键 词:隧洞衬砌  全圆针梁台车  抗浮计算  南水北调配套工程  南干渠工程  北京市  
收稿时间:2012-09-27

Design of anti-uplift structure of full circle needle beam formwork trolley for tunnel lining
ZHANG Junying. Design of anti-uplift structure of full circle needle beam formwork trolley for tunnel lining[J]. Water Resources and Hydropower Engineering, 2012, 43(12): 48-51
Authors:ZHANG Junying
Affiliation:(China Railway 13th Bureau Group Co., Ltd., Tianjin300308, China)
Abstract:The shallow-buried and underground-excavated water conveyance tunnel of the bit section No.7 of the South Main Canal——an auxiliary project in Beijing for the South Main Canal of the South-to-North Water Transfer Project is a double-route water conveyance tunnel with the nominal diameter(DN) of 3 400 mm, for which the secondary lining is constructed with a full circle needle beam formwork trolley. To deal with the problem from the uplift of the trolley usually occurred during concreting for the lining, a detailed calculation on the anti-uplift of the trolley is made from the very beginning of the design of it.The actual concreting for the lining demonstrates that the anti-uplift device of the trolley can effectively prevent the uplift of it during the construction, and then accumulates some relevant experiences for the similar project in the days to come.
Keywords:tunnel lining  full circle needle beam formwork trolley  auxiliary project for South-to-North Water Transfer Project  South Main Canal Project  Beijing  