高坝洲水电站深孔消力池基础岩溶涌水点处理
引用本文:刘定华. 高坝洲水电站深孔消力池基础岩溶涌水点处理[J]. 湖北水力发电, 2001, 0(2): 12-14
作者姓名:刘定华
作者单位:湖北清江水电开发有限责任公司 宜昌
摘    要:对深孔消力池内的两股岩溶涌水点,曾采取过许多处理措施,未见成效,最后总结经验,确立了“变动水为静水”的指导思想,制定了“先浇并锚后灌”的总体施工方案,成功的堵住了涌水,达到了预期目的。

关 键 词:岩溶涌水点  变动水为静水  先浇并锚后灌
修稿时间:2000-10-25

Treatment for Karst Springs in the Foundation of Stilling Pool of Gobazhou Hydropower Station
Lau Dinghua. Treatment for Karst Springs in the Foundation of Stilling Pool of Gobazhou Hydropower Station[J]. Hubei Water Power, 2001, 0(2): 12-14
Authors:Lau Dinghua
Abstract:For the sake of blocking up the karst fissures in the foundation of stilling pool, a construction scheme is worked out, that is under the guide thinking of "changing the karst groundwater from running to still", and "casting the slab concrete and anchoring earlier, foundation grouting later", at last, the karst fissures are blocked up.
Keywords:karst spring   still pool   treatment of foundation  