铜坑矿4~#风井贯通测量方案与误差预计
引用本文:兰宇. 铜坑矿4~#风井贯通测量方案与误差预计[J]. 金属材料与冶金工程, 2014, 0(2): 58-60
作者姓名:兰宇
作者单位:广西华锡集团股份有限公司,广西南丹547207
摘    要:通过对铜坑矿4#风井贯通测量方案的误差预计,确定拟采用的测量方案的可行性;同时通过贯通工程施工前的误差预计和贯通后实际测量的精度对比,说明测量方案取得了成功。

关 键 词:贯通测量  误差预计

Scheme and Error Estimate of Through Survey of No.4 Ventilation Shaft of Tongkeng Mine
LAN Yu. Scheme and Error Estimate of Through Survey of No.4 Ventilation Shaft of Tongkeng Mine[J]. Metal Materials And Metallurgy Engineering, 2014, 0(2): 58-60
Authors:LAN Yu
Affiliation:LAN Yu (Guangxi China Tin Group Co., Ltd., Nandan 547207, China)
Abstract:Based on the error estimate of the through survey scheme for No.4 ventilation shaft of Tongkeng Mine, a determination was made to the feasibility of the survey scheme to be adopted. By comparing the error estimate before the construction of the holing-through project with the actual data measured precisely after holing through, it is indicated that the survey scheme is successful.
Keywords:through survey  error estimate