摘    要:凤凰水电厂二级电站五号机组自投产起最大出力一直达不到设计出力标准 (30 0 0KW)。通过效率测试和分析 ,探讨机组出力不足的原因并进行技术改造 ,取得了一定的效果

关 键 词:水机效率  测试  分析  通气高度  技改
文章编号:1672-2841(2004)04-0056-03
修稿时间:2004-03-30

Analysis of Causes of Inadequate Output in Part of Units in Fenghuang Hydropower Station
PENG Rui-jin. Analysis of Causes of Inadequate Output in Part of Units in Fenghuang Hydropower Station[J]. Journal of Guangdong Technical College of Water Resources and Electric Engineering, 2004, 2(4): 56-58
Authors:PENG Rui-jin
Abstract:The fifth unit in the second station of Fenghuang Hydropower Station has never reached the maximum designed criterion (3000KW) since it was put into production.Through efficiency testing and analysis, we have succeeded in finding out the causes and carried out technological innovation.
Keywords:turbine's efficiency  testing  analyzing  aeration height  technology innovation