龙背湾水电站坝体主堆石料运输干道方案的设计与比选 |
| |
引用本文: | 沈立群,喻建春. 龙背湾水电站坝体主堆石料运输干道方案的设计与比选[J]. 湖北水力发电, 2016, 0(3): 30-33. DOI: 10.13622/j.cnki.cn42-1800/tv.1671-3354.2016.03.008 |
| |
作者姓名: | 沈立群 喻建春 |
| |
作者单位: | 湖北省水利水电规划勘测设计院,湖北武汉,430070 |
| |
摘 要: | 以龙背湾水电站为例,介绍了大坝主堆石料的运输要求,提出了运输干道布置的设计方案,从方案的特性及工程投资等方面进行了比选,确定了最优方案。特别介绍了采用交通洞方案的优点及应用效果。
|
关 键 词: | 填筑强度 运输强度 运输干道 交通洞 |
Design and Selection of the Main Transportation Scheme for Main Rockfill Materials in Longbeiwan Hydropower Station |
| |
Abstract: | The transportation requirement for main rockfill materials in Longbeiwan Hydropower Station is introduced. Then, several designs of the main transportation scheme are presented and compared from the engineering and invest-ment prospects.Specifically, the transportation tunnel scheme is introduced, including its advantages and actual per-formance. |
| |
Keywords: | filling intensity transportation intensity main transportation road transportation tunnel |
本文献已被 CNKI 万方数据 等数据库收录! |
|