尾砂胶结充填新工艺在武山铜矿的研究与应用
引用本文:林国洪. 尾砂胶结充填新工艺在武山铜矿的研究与应用[J]. 铜业工程, 2008, 0(3): 7-9
作者姓名:林国洪
作者单位:江西铜业集团公司武山铜矿,江西瑞昌,332204
摘    要:为满足技改需求,扩大生产能力,武山铜矿的二期扩产设计采用下向分级尾砂胶结充填新工艺试验研究,通过研究改进胶结充填工艺过程、取消钢筋混凝土人工假底、扩大回采断面来扩大生产规模,提高工作效率。

关 键 词:大断面开采  尾砂胶结充填  工艺研究

A Study on Cemented Tailing Backfill New Process under Large Section Mining Condition and its Application in Wushan Copper Mine
LIN Guo-hong. A Study on Cemented Tailing Backfill New Process under Large Section Mining Condition and its Application in Wushan Copper Mine[J]. Copper Engineering, 2008, 0(3): 7-9
Authors:LIN Guo-hong
Affiliation:LIN Guo - hong ( Wushan Copper Mine Jiangxi Copper Corporation, Ruichang 332204, Jiangxi, China)
Abstract:In order to meet the requirement of technical modification and production capacity improvement, a test study is conducted in Wushan Copper Mine for phase II production expansion by adopting underhand classified cemented tailing backfill process to increase production scale and improve working efficieney.
Keywords:large section mining  cemented tailing backfill  process study