大朝山水电站截流工程有关设计工作的回顾
引用本文:林可冀.大朝山水电站截流工程有关设计工作的回顾[J].云南水力发电,1998,14(1):15-16.
作者姓名:林可冀
作者单位:电力部水利部北京勘测设计研究院
摘    要:本文针对大朝山水电站工程总布置、施工导流规划以及工程总进度的特点,回顾和总结了截流工程设计中三个重大技术问题的决策过程和经验教训。

关 键 词:大朝山水电站  截流  施工导流  导流隧洞  围堰

Review of The Design Work of The River Closure Works for The Dachaoshan Hydropower Project
Lin,Keji.Review of The Design Work of The River Closure Works for The Dachaoshan Hydropower Project[J].Yunnan Water Power,1998,14(1):15-16.
Authors:Lin  Keji
Abstract:This paper reviews and summarises the decision-making process for three major technical issues in the design of the river closure works and their experience and lesson in accordance with the general layout,the construction diversion planning and the general construction schedule of the Dachaoshan Hydropower project.
Keywords:Dachaoshan Hydropower project    Decision_making process    General layout Construction diversion Planning  General construction schedule
本文献已被 CNKI 维普 等数据库收录!