首页 | 本学科首页   官方微博 | 高级检索  
     

浅谈水电站前期准备工程施工索赔
引用本文:蒋兴.浅谈水电站前期准备工程施工索赔[J].山西建筑,2009,35(26):241-242.
作者姓名:蒋兴
作者单位:中铁二十三局集团第三工程有限公司,四川,成都,610000
摘    要:结合具体工程实例,介绍了常见的几种索赔原因及其计算方法,阐述了索赔事件发生后,具体的操作步骤及处理程序,并提出了索赔中应特别注意的问题,指出作为施工单位,索赔事件应贯穿全过程,以期降低施工成本,提高经济效益。

关 键 词:水电站  索赔  操作步骤  索赔报告

On claims in primary preparation works in hydropower stations
JIANG Xing.On claims in primary preparation works in hydropower stations[J].Shanxi Architecture,2009,35(26):241-242.
Authors:JIANG Xing
Abstract:By combining with project examples,the paper introduces some claim reasons and calculative methods,illustrates some factual steps and treatment procedures after the claim accidents,and points out some precautions in the claims,and points out the claim accidents should go along the whole process in the construction enterprises,so as to reduce the construction costs and improve the economic benefits.
Keywords:hydropower station  claim  operative steps  claim report
本文献已被 维普 万方数据 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号