Teilfertigdecken nach DIN 1045‐1. Wichtige Punkte der Bemessung und Konstruktion |
| |
Authors: | Hartmut Land |
| |
Abstract: | Partly pre‐fabricated reinforced concrete Floors/Ceilings according to DIN 1045‐1. Important Points of Design and Construction There are invasive changes in design and construction of partly pre‐fabricated reinforced concrete floors/ceilings connected with the application of DIN 1045‐1, July 2001 issue. This applies specifically to the verification of acceptance of thrust force in the joint between pre‐cast slab and the on‐site concrete. The basic elements will be gathered for this extensive verification and an example is given. Regulations for the arrangement of lattice girders as bond/shear force reinforcement as well as concrete covers will be shown in detail. Structures of support are easier to implement in the future. |
| |