破碎围岩预控分段嗣后充填技术研究与实践
引用本文:董国强.破碎围岩预控分段嗣后充填技术研究与实践[J].有色金属(矿山部分),2018,70(4).
作者姓名:董国强
作者单位:招金矿业股份有限公司大尹格庄金矿
摘    要:针对破碎围岩稳定性差、深部矿压显现剧烈等难题,结合大尹格庄金矿现有采矿工艺,提出预控顶分段嗣后充填技术。在阐述预控顶分段嗣后充填技术特点、施工工艺、技术关键的基础上,采用正交实验优化充填材料配比,重点采用理论分析和数值模拟相结合的方式优化设计采场结构参数。实践表明,预控顶分段嗣后充填技术在各矿得到广泛应用,效益显著。

关 键 词:破碎岩体  预控顶分段嗣后充填技术  充填配比  
收稿时间:2018/1/26 0:00:00
修稿时间:2018/3/1 0:00:00

Study and Application on Precontrolling of Roof and Sublevel Open-slope Mining with Subsequent Filling Method for Fractured Surrounding Rock
Authors:DONG Guo-qiang
Affiliation:Yingezhuang gold ore Zhaojin Mining Industry
Abstract:In view of the difficulties in the poor stability of the fractured surrounding rock and the violent appearance of the deep mine pressure, and combined with the existing mining technology in Dayingezhuang gold, Proposed Precontrolling of Roof and Sublevel Open-slope Mining with Subsequent Filling Method . On the basis of technical characteristics, construction technology and key technology about Precontrolling of Roof and Sublevel Open-slope Mining with Subsequent Filling Method,Orthogonal experiment is used to optimize the ratio of filling material.Optimization design of stope structural parameters by combining theoretical analysis with numerical simulation. Practice shows that the precontrolling of roof backfilling technology segment has been widely used in various mines, significant benefits.
Keywords:Fractured Surrounding Rock  Precontrolling of Roof and Sublevel Open-slope Mining with Subsequent Filling Method  Filling ratio  