彭水水电站导流洞混凝土封堵施工
引用本文:高鄂湘,王刚. 彭水水电站导流洞混凝土封堵施工[J]. 西北水电, 2014, 0(6): 97-100
作者姓名:高鄂湘  王刚
作者单位:中国水利水电建设工程咨询西北有限公司,西安710065
摘    要:在彭水水电站大坝导流洞永久堵头的封堵过程中,由于2号导流洞闸门下游渐变段出现大量漏水的现象,渗水量大约为1.3 m3/s,造成洞内积水,为此采取在永久堵头上下游设置混凝土临时堵头挡水,确保永久堵头干地施工。

关 键 词:导流洞  封堵  施工法  综述  彭水水电站

Plugging Construction of Diversion Tunnel,Pengshui Hydropower Project
GAO E-xiang,WANG Gang. Plugging Construction of Diversion Tunnel,Pengshui Hydropower Project[J]. Northwest Water Power, 2014, 0(6): 97-100
Authors:GAO E-xiang  WANG Gang
Affiliation:(China Hydro Consulting Engineering Corporation, Northwest Branch, Xian 710065, China)
Abstract:During the construction of the permanent plug for the diversion tunnel of Pengshui Hydropower Project, leakage in a large quan-tity occurs at the transition section at the downstream of the Diversion Tunnel No.2 gate, resulting in water accumulated in the tunnel. The seepage flow is about 1.3 m3/s.Therefore, the temporary concrete plugs are proposed to build on both sides of the permanent plug to retaining the seepage so that the permanent plug can be constructed in dry condition.
Keywords: