首页 | 本学科首页   官方微博 | 高级检索  
     


Concessionaire Selection for Build-Operate-Transfer Tunnel Projects in Hong Kong
Authors:X. Q. Zhang  M. M. Kumaraswamy  W. Zheng  E. Palaneeswaran
Affiliation:1Research Assistant, Dept. of Civil Engineering, The Univ. of Hong Kong, Pokfulam Rd., Hong Kong, China.
2Associate Professor, Dept. of Civil Engineering, The Univ. of Hong Kong, Pokfulam Rd., Hong Kong, China.
Abstract:A significant realignment of risks between project participants is a fundamental facet of the new procurement paradigm of BOT (build-operate-transfer). A BOT concessionaire assumes far more and deeper risks than a contractor. One critical contributor to the success of a BOT project is the selection of an appropriate concessionaire who has the necessary capacity to provide the best overall deal throughout the build-operate-transfer process. However, various BOT-type procurement protocols are not yet proven and are still being tried and tested. Many countries are at the lower ends of their learning curves. Therefore, there is a need to benchmark the best practices that have been emerging. The Hong Kong government has developed a well-structured concessionaire selection framework supported by the Kepner-Tregoe decision analysis technique. This paper analyzes and draws experiences and lessons from this concessionaire selection practice. Current concessionaire selection practices worldwide are also discussed with a view to improve the procurement process of regions lacking in such experiences or expertise.
Keywords:Build/operate/transfer  Tunnel construction  Hong Kong  
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号