500 kV斗山变改造中二次部分遇到的问题及解决方法
引用本文:鲍有理,吕峰,奚雪峰.500 kV斗山变改造中二次部分遇到的问题及解决方法[J].华东电力,2007,35(8):26-28.
作者姓名:鲍有理  吕峰  奚雪峰
作者单位:无锡供电公司,江苏,无锡,214061
摘    要:对在500 kV斗山变改造过程中出现的直流控制回路、交流回路的异常作了阐述,提出了解决方案和防范措施.还对重点部分入差动保护用的TA三侧极性试验作了说明,结论正确.

关 键 词:改造顺序  回路正确性验证  TA极性验证  危险源点分析
文章编号:1001-9529(2007)08-0026-03
修稿时间:2007年8月7日

Problems encountered in retrofit of secondary system of 500 kV Doushan Substation and relevant solutions
BAO You-li,LU Feng,XI Xue-feng.Problems encountered in retrofit of secondary system of 500 kV Doushan Substation and relevant solutions[J].East China Electric Power,2007,35(8):26-28.
Authors:BAO You-li  LU Feng  XI Xue-feng
Abstract:The abnormal phenomena of the DC control circuit and the AC circuit during retrofit process of 500 kV Doushan Substation are illuminated,and solutions and countermeasures are proposed.The three-side polarity test of TA used for connection with the differential protection is also analyzed.
Keywords:retrofit order  circuit correction validation  TA polarity test  hazard point analysis