污水处理厂提标改造措施选择与工程实践 |
| |
引用本文: | 王立东,王阿华. 污水处理厂提标改造措施选择与工程实践[J]. 中国给水排水, 2010, 26(8) |
| |
作者姓名: | 王立东 王阿华 |
| |
作者单位: | 南京市市政设计研究院有限责任公司,江苏,南京,210008 |
| |
摘 要: | 通过提标改造和扩建,某污水处理厂的处理能力从2.5×104 m3/d提高至5.0×104m3/d,出水水质由一级B标准提高至一级A标准。通过将常规A2/O工艺改造为倒置A2/O工艺、优化工艺运行、局部改造和增加深度处理设施等措施,对BOD5、SS、NH3-N和TP的去除率分别达到95.0%、96.2%、82.1%和90.4%,出水水质达到一级A标准。详细介绍了提标改造内容及采取的措施,可为类似工程的设计提供参考。
|
关 键 词: | 提标改造 倒置A~2/O工艺 脱氮除磷 一级A标准 |
Measures and Practice on Upgrading Reconstruction of Wastewater Treatment Plant |
| |
Abstract: | After upgrading reconstruction and extension construction, the treatment capacity of a wastewater treatment plant was increased from 2.5×10~4 m~3/d to 5.0×10~4 m~3/d, and the effluent quality was improved from the first class B criteria to the first class A criteria. After the proposed measures, such as reconstructing the traditional A~2/O process into reversed A~2/O process, optimizing the process opera-tion condition, partial retrofitting and adding advanced wastewater treatment facilities were taken, the re-moval rates of BOD_5, SS, NH_3- N and TP were 95.0%, 96.2%, 82.1% and 90.4% respectively, and the up-to-standard discharge of the effluent was achieved. The content and measures applied during the upgrading reconstruction and extension construction are introduced, providing reference for other simi-lar projects. |
| |
Keywords: | upgrading reconstruction reversed A~2/O process nitrogen and phosphorus re-moval first class A criteria |