并联电容器装置现场施工质量的监理
引用本文:陈静元,王维义.并联电容器装置现场施工质量的监理[J].电力电容器,2005(4):38-40.
作者姓名:陈静元  王维义
作者单位:唐山供电公司 河北唐山063000
摘    要:并联电容器组在变电站的运行中有相当一部分故障是因为施工质量差而引起。本文主要讨论在并联电容器工程施工中由于隐蔽工程、电容量不平衡、熔断器安装角度不正确、接头发热及放电线圈接线不正确等对电容器组运行的影响。为此,要高度重视并联电容器工程施工质量的监理。

关 键 词:电容器组  施工质量  监理
文章编号:1002-0349(2005)04-0038-03
修稿时间:2005年9月5日

Inspections on Construction Quality of the Shunt Capacitor
CHEN Jing-yuan,WANG Wei-yi.Inspections on Construction Quality of the Shunt Capacitor[J].Power Capacitors,2005(4):38-40.
Authors:CHEN Jing-yuan  WANG Wei-yi
Abstract:Most of the breakdowns in shunt capacitor banks during the substation operation is due to the construction quality.This paper mainly discusses the factors that influence on the shunt capacitor bank operation,such as concealed work,unbalanced capacitance,incorrect installation angle of the fuse,connector overheating and incorrect connection of discharge coil.It must,therefore,pay more attentions to the construction quality of shunt capacitor project.
Keywords:Capacitor bank  Construction quality  Inspection