首页 | 本学科首页   官方微博 | 高级检索  
     

“引大济湟”×××隧洞围岩变形探讨
引用本文:彭良余. “引大济湟”×××隧洞围岩变形探讨[J]. 资源环境与工程, 2012, 26(5): 527-529,538
作者姓名:彭良余
作者单位:长江勘测规划设计研究有限责任公司,湖北武汉,430010
摘    要:青海省引大济湟调水总干渠工程×××隧洞主要采用双护盾式TBM施工.在穿越高埋深的区域性断裂带时,采用绕行导坑人工钻爆法施工.对采用绕行导坑的围岩变形情况进行分析,指出在隧洞开挖过程中围岩变形的时间效应,为修改设计与指导施工提供理论依据.

关 键 词:回归分析  变形观测  绕行导坑

Study on Tunnel Surrounding Rock Deformation of Diversion of Datonghe River to Huangshuihe River
PENG Liangyu. Study on Tunnel Surrounding Rock Deformation of Diversion of Datonghe River to Huangshuihe River[J]. Resources Environment & Engineering, 2012, 26(5): 527-529,538
Authors:PENG Liangyu
Affiliation:PENG Liangyu(Changjiang Institute of Survey,Planning,Design and Research,Wuhan,Hubei 430010)
Abstract:Double shield TBM was adopted mainly in the tunnel construction of Diversion of Datonghe River to Huangshuihe River.When the tunnel crossed deep buried regional fracture zone,detouring drift method and drilling and blasting method were used for the tunnel construction.The surrounding rock deformation was analyzed in the paper,and the time effect of surrounding rock deformation during tunnel excavation was pointed out,which could provide theoretical basis for design and construction.
Keywords:regression analysis  deformation observation  detouring drift method