二矿主井井架改造施工工艺
引用本文:孙清华. 二矿主井井架改造施工工艺[J]. 煤矿机械, 2007, 28(10): 159-160
作者姓名:孙清华
作者单位:鹤壁富昌建设工程有限责任公司,河南,鹤壁,458020
摘    要:针对矿井旧井架改造施工工艺,主要介绍了施工改造的总体方案及矿井停产前井架的制作、防腐及安装准备工作,并介绍了矿井停产后提升设施拆除、斜架抬头、立架吊装、立架和斜架的合拢等施工工艺。运用该施工工艺工期可缩短2~3 d;运用大型吊车避免了起立桅杆的繁琐;占用井口时间短。

关 键 词:矿井旧井架  改造  施工工艺  效果与效益
文章编号:1003-0794(2007)10-0159-02
修稿时间:2007-04-19

The Second Mine Main Well Headframe Reformation Construction Craft
SUN Qing-hua. The Second Mine Main Well Headframe Reformation Construction Craft[J]. Coal Mine Machinery, 2007, 28(10): 159-160
Authors:SUN Qing-hua
Affiliation:Hebi Fuchang Construction Engineering Limited Liability Company, Hebi 458020, China
Abstract:Aim at mineral well an old well a reformation construction craft, main introduction construction reformation of total project and mineral well stop production ex - well of creation, antisepsis and install preparation work, and introduction the mineral well promote facilities to tore down after stop production, inclined rise, sign a mourn to pack, sign and inclined of gather together etc., construction craft. Usage should construction craft work period can shorten for 2 - 3 days; the usage large hoist avoided stooding up a mast of tedious; take up mouth of a well short for time.
Keywords:mineral well old headfrarne   reformation   construction craft   effect and performance