阳江抽水蓄能电站高压隧洞段工程地质条件分析
引用本文:杨磊.阳江抽水蓄能电站高压隧洞段工程地质条件分析[J].广东水利水电,2017(4):40-44.
作者姓名:杨磊
作者单位:广东省水利电力勘测设计研究院,广东 广州,510635
摘    要:通过分析阳江抽水蓄能电站高压隧洞段的工程地质条件,从隧洞的覆盖层厚度、围岩水力劈裂、围岩渗透稳定性方面进行分析判别,结果高压隧洞段Ⅰ~Ⅱ类围岩满足采用钢筋混凝土衬砌的工程地质条件,但断层和裂隙密集带发育的Ⅲ~Ⅳ类围岩在高水头压力作用下会发生渗透破坏,需专门进行固结灌浆处理。

关 键 词:高压  覆盖比  围岩  钢筋混凝土衬砌
收稿时间:2017/2/16 0:00:00
修稿时间:2017/2/16 0:00:00

Analysis on Engineering Geological Condition of High Pressure Tunnel in Yangjiang Pumped Storage Power Station
YANG Lei.Analysis on Engineering Geological Condition of High Pressure Tunnel in Yangjiang Pumped Storage Power Station[J].Guangdong Water Resources and Hydropower,2017(4):40-44.
Authors:YANG Lei
Affiliation:Guangdong Hydropower Planning & Design Institute,Guangzhou 510635, China
Abstract:Through the analysis on high pressure tunnel engineering geological condition of Yangjiang pumped storage power station, from the aspect of cover thickness of tunnel surrounding rock, hydraulic fracturing and rock seepage stability, the I-II surrounding rock of high pressure tunnel meet the engineering geological conditions of the reinforced concrete lining, but seepage appears at the surrounding rock of the fault and fissure zone III ~ IV under high water pressure, so it needs specialized consolidation grouting.
Keywords:high pressure  coverage ratio  surrounding rock  reinforced concrete lining
本文献已被 CNKI 万方数据 等数据库收录!