金川二矿区1000m中段水平矿柱形成及回采技术研究
引用本文:汪小平,程国龙,李建东,康陇平,程国祥. 金川二矿区1000m中段水平矿柱形成及回采技术研究[J]. 有色金属(矿山部分), 2020, 72(4): 33-37
作者姓名:汪小平  程国龙  李建东  康陇平  程国祥
作者单位:金川集团有限公司,金川集团有限公司,金川集团有限公司,金川集团有限公司,金川集团有限公司
摘    要:金川二矿区采用双中段同时开采方式,随着两中段之间剩余矿体垂直厚度变薄,逐渐形成水平矿柱,及时准确地判定水平矿柱形成并安全将其回采,对于矿山的可持续发展至关重要。采用数值模拟手段分析了水平矿柱随着开采深度变化的形成过程,提出水平矿柱厚度为20m以下,矿柱完全破坏。通过对1 000m中段水平矿柱安全高效回采进行探索和研究,形成了矿柱回采的方案,最大限度地避开了现有在用的重点工程,保障了二矿区安全生产和出矿任务在后续中段衔接过程中有序进行。

关 键 词:水平矿柱;两中段开采;数值模拟;回采方案
收稿时间:2020-02-26
修稿时间:2020-03-08

Study on the formation and mining technology of 1000m middle horizontal pillar in Jinchuan No.2 Mining Area
WANG Xiaoping,CHENG Guolong,LI Jiandong,KANG Longping and CHENG Guoxiang. Study on the formation and mining technology of 1000m middle horizontal pillar in Jinchuan No.2 Mining Area[J]. , 2020, 72(4): 33-37
Authors:WANG Xiaoping  CHENG Guolong  LI Jiandong  KANG Longping  CHENG Guoxiang
Affiliation:Jinchuan Group Ltd.,Jinchang,Gansu,737100,Jinchuan Group Ltd.,Jinchang,Gansu,737100,Jinchuan Group Ltd.,Jinchang,Gansu,737100,Jinchuan Group Ltd.,Jinchang,Gansu,737100,Jinchuan Group Ltd.,Jinchang,Gansu,737100
Abstract:The No.2 Mining Area of Jinchuan adopts the mining method of double middle section at the same time. As the vertical thickness of the remaining ore body between the two middle sections becomes thinner, the horizontal pillar is gradually formed. It is very important for the sustainable development of the mine to determine the formation of the horizontal pillar in time and accurately and to mine it safely. In this paper, the numerical simulation method is used to analyze the formation process of the horizontal pillar with the change of mining depth. It is proposed that the thickness of the horizontal pillar is less than 20 m and the pillar is completely destroyed. Through the exploration and research on the safe and efficient mining of the 1000m middle section horizontal pillar, a scheme of pillar mining has been formed, which avoids the existing key projects in use to the maximum extent, and ensures the safe production and mining task of the No.2 Mining Area to be carried out orderly in the following middle section connection process.
Keywords:Horizontal pillar   two middle mining   numerical simulation   mining plan