复杂地基条件下土石围堰施工防渗研究
引用本文:徐晓飞,李春贵.复杂地基条件下土石围堰施工防渗研究[J].黄河水利职业技术学院学报,2008,20(2):3-6.
作者姓名:徐晓飞  李春贵
作者单位:武警水电一总队,广西,南宁,530022
摘    要:某水电站上游围堰在围堰左岸基础位于基岩上,右岸基础位于松动体上,中间河床覆盖层自下而上分为三类岩组,其中Ⅰ、Ⅲ类岩组岩层属强透水层,Ⅱ类岩组属中等一强透水层。围堰挡水后将产生集中绕坝渗漏。为解决上游围堰防渗及绕坝渗漏问题,确定最优防渗方案,对上游围堰及基础进行了三维有限元渗流计算。计算结果表明,确定河床覆盖层必须修筑混凝土防渗墙进行防渗,但根据实际的地形条件以及施工难度情况,对右岸松动体的防渗方案做了相应优化,确定采用防渗帷幕进行松动体内的防渗。

关 键 词:土石围堰  复杂地基  有限元方法  施工防渗  无压渗流分析
文章编号:1008-486(2008)02-0003-04
修稿时间:2007年12月15

Research on Construction Anti-seepage of Earth-rock Cofferdam of Complex Foundation
XU Xiao-fei,LI Chun-gui.Research on Construction Anti-seepage of Earth-rock Cofferdam of Complex Foundation[J].Journal of Yellow River Conservancy Technical Institute,2008,20(2):3-6.
Authors:XU Xiao-fei  LI Chun-gui
Affiliation:(First General Team of Armed Police Hydropower, Nanning 530022, Guangxi, China)
Abstract:The left bank foundation of one hydropower station upstream is on bedrock,the right bank foundation is on the loosening body.The upstream overburn layer is devided into three kinds of rocks.The I and III rock layer are the strong leakage layers,and the II layer is medium leakage layer.Central dam circle leakage will appear after retaining the water of cofferdam.To calculate the three-dimensional finite element of the upstream cofferdam and foundation in order to solve the problems of anti-seepage and dam circle leakage of upstream cofferdam and choose the optimum plan.The calculation shows that we must build the concrete anti-seepage wall of the river body overburn layer.According to the real terrain condition and the difficulty of construction,we optimize the anti-seepage plan to the loosening body of the right river bank and decide to choose the anti-seepage curtain to prevent the seepage of the loosening body.
Keywords:earth-rock cofferdam  complex foundation  the method of finite element  construction anti-seepage  seepage analysis without pressure