模糊评价与PSO优化的LSSVM架空输电线路故障率预测
引用本文:方权,刘闯,宋敏,唐波,侯寻,杨世强,郑浩. 模糊评价与PSO优化的LSSVM架空输电线路故障率预测[J]. 水电能源科学, 2021, 39(1): 171-175
作者姓名:方权  刘闯  宋敏  唐波  侯寻  杨世强  郑浩
作者单位:国网湖北省电力有限公司检修公司,湖北宜昌443002;国网湖北省电力有限公司荆门供电公司,湖北荆门448000;三峡大学电气与新能源学院,湖北宜昌443002
基金项目:国家自然科学基金项目(51977121)。
摘    要:准确计算架空线路故障率对于保障线路安全稳定运行有重要意义.分析确定架空输电线路故障的影响因素,将其划分为4个一级指标和21个二级指标,建立线路故障指标评价体系.分别采用三角分布法和模糊试验法确定定量指标和定性指标的隶属度函数,利用九分度AHP法计算各指标权重,通过模糊运算得到各影响因素的评价值.根据故障造成损失的严重程...

关 键 词:架空输电线路  故障率  模糊评价  粒子群  最小二乘支持向量机

Failure Rate Prediction of Overhead Transmission Line Based on Fuzzy Evaluation and PSO-Optimized LSSVM
FANG Quan,LIU Chuang,SONG Min,TANG Bo,HOU Xun,YANG Shi-qiang,ZHENG Hao. Failure Rate Prediction of Overhead Transmission Line Based on Fuzzy Evaluation and PSO-Optimized LSSVM[J]. International Journal Hydroelectric Energy, 2021, 39(1): 171-175
Authors:FANG Quan  LIU Chuang  SONG Min  TANG Bo  HOU Xun  YANG Shi-qiang  ZHENG Hao
Affiliation:(Maintenance Company State Grid Hubei Electric Power Supply Co.,Ltd.,Yichang 443002,China;State Grid Hubei Jingmen Power Supply Company,Jingmen 448000,China;College of Electrical Engineering&New Energy,China Three Gorges University,Yichang 443002,China)
Abstract:Accurate calculation of the fault rate of overhead transmission line is great significance for ensuring the safe and stable operation of the line.This paper analyzed the factors affecting the fault of overhead transmission line and divided them into 4 primary indexes and 21 secondary indexes.The evaluation index system of line fault was established.The membership function of quantitative index and qualitative index were determined by means of triangle distribution method and fuzzy test method,respectively.In addition,each index weight was calculated by nine-degree AHP method,and the evaluation value of each influencing factor was obtained by fuzzy operation.According to the severity of the losses caused by the faults,the faults were classified into three categories:defects,failures and accidents.Parameters of the LSSVM were optimized by particle swarm optimization.Taking the running time and 4 primary indexes as the support vectors,the prediction model of grade-I line fault rate was established.After verification,the average relative error of the model was 2.36%.Finally,an example was given to verify the effectiveness of the method of line fault rate mentioned in the paper.The calculation results can be used to provide reference for the preparation of operational measures by electric power department.
Keywords:overhead transmission line  fault rate  fuzzy evaluation  particle swarm  least squares support vector machine