Differences between Calculated and Measured Long-Term Deflections in a Prestressed Concrete Girder Bridge
Authors:P. J. Barr  F. Angomas
Affiliation:1Associate Professor, Dept. of Civil and Environmental Engineering, Utah State Univ., 4110 Old Main Hill, Logan, UT 84332-4110 (corresponding author).
2Graduate Student, Dept. of Civil and Environmental Engineering, Utah State Univ., 4110 Old Main Hill, Logan, UT 84332-4110.
Abstract:The monitoring of five precast, prestressed bridge girders during fabrication and service provided the opportunity to observe changes in camber over time. These camber variations were compared with corresponding strain and temperature measurements. Each of the girders was cast outside during the winter. As a result, the cold ground acted as a heat sink, and a significant temperature gradient existed during curing of each of the instrumented girders. These temperature gradients are believed to have caused the wide range in the short- and long-term cambers. A procedure to calculate the effect that curing temperatures have on girder camber is presented. In addition, the measured camber values are compared with predicted values using the multiplier method, improved multiplier method, and a detailed time-step method. It was found for the long-span girders that the measured camber values were on average within 10% of the predicted values using the detailed time-step method, but ranged from 22% lower to 27% higher for the simpler methods.
Keywords:Bridges, concrete  Bridges, girder  Precast concrete  High-strength concrete  Design  