交联聚乙烯(XLPE)电缆交流耐压试验时间参数探讨 |
| |
作者姓名: | 温定筠 吕景顺 范迪铭 彭 鹏 孙亚明 马建海 王成生 |
| |
作者单位: | 甘肃电力科学研究院,兰州 730050;甘肃电力科学研究院,兰州 730050;甘肃电力科学研究院,兰州 730050;甘肃电力科学研究院,兰州 730050;甘肃电力科学研究院,兰州 730050;甘肃电力科学研究院,兰州 730050;甘肃电力科学研究院,兰州 730050 |
| |
基金项目: | 甘肃省电力公司重大科技项目(2008406022) |
| |
摘 要: | 对比了国内外各标准对110 kV XLPE电缆交流耐压试验时间参数选取的不同要求;通过固体电介质击穿理论的分析,提出由局部性缺陷发展逐渐导致介质击穿需要较长的发展时间。总结现场试验经验发现,除少数极为严重的缺陷会在极短时间内暴露外,大部分缺陷是从局部逐渐发展导致电缆击穿,选择5 min试验时间不足以使缺陷暴露的,而选择60 min是较为合理的。
|
关 键 词: | 交联聚乙烯(XLPE) 交流耐压 试验时间 击穿 |
Discussions on Time Parameters for Alternating Voltage Tests on XLPE Cables |
| |
Authors: | WEN Ding-jun LV Jing-shun FAN Di-ming PENG Peng SUN Ya-ming MA Jian-hai and WANG Cheng-sheng |
| |
Affiliation: | Gansu Electric Power Research Institute, Lanzhou 730050,Gansu Province, China;Gansu Electric Power Research Institute, Lanzhou 730050,Gansu Province, China;Gansu Electric Power Research Institute, Lanzhou 730050,Gansu Province, China;Gansu Electric Power Research Institute, Lanzhou 730050,Gansu Province, China;Gansu Electric Power Research Institute, Lanzhou 730050,Gansu Province, China;Gansu Electric Power Research Institute, Lanzhou 730050,Gansu Province, China;Gansu Electric Power Research Institute, Lanzhou 730050,Gansu Province, China |
| |
Abstract: | This paper compared the different criteria in selecting the test time parameter for 110 kV cross-linked polyethylene(XLPE) cables in the different codes and standards both at home and abroad. Based on analyses in line with the solid dielectric breakdown theory, it concluded that it takes a long time for a partial fault to develop gradually to the dielectric breakdown. According to the actual site tests, except a small number of serious faults which could be exposed in a very short time, most faults, started from partial ones, turned into breakdowns slowly over time. Selection of 5 minutes as the test time is inadequate for explosion of faults, while the relatively more appropriate test time should be 60 minutes. |
| |
Keywords: | |
|
| 点击此处可从《》浏览原始摘要信息 |
|