首页 | 本学科首页   官方微博 | 高级检索  
     

大容量并联电容器组设计和运行的若干问题
引用本文:林瑞宗. 大容量并联电容器组设计和运行的若干问题[J]. 电力电容器, 2002, 0(4): 26-31
作者姓名:林瑞宗
作者单位:福建省超高压输变电局 厦门361004
摘    要:从运行经验出发讨论220-500kV变电站中电容器组设计和运行的有关问题,包括电容器组的接线方案,结构型式和防止谐波放大及谐波共振的措施等。

关 键 词:大容量并联电容器组 设计 运行 无功补偿 变电站
文章编号:1002-0349(2002)04-0026-06
修稿时间:2002-11-08

Problems in Design and Operation of the
LIN Rei zong. Problems in Design and Operation of the[J]. Power Capacitors, 2002, 0(4): 26-31
Authors:LIN Rei zong
Abstract:Based on operation experiences, this paper discusses some problems related to design and operation of the capacitor bank, used in 220 500kV substations. These problems include the way of connection and the construction type of the capacitor bank, and measures to prevent its harmonic amplification and harmonic resonance.
Keywords:Reactive power compensation   Shunt capacitor   Design   Operation  
本文献已被 CNKI 维普 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号