湖北省荆州电网的发展与展望
引用本文:曾亮.湖北省荆州电网的发展与展望[J].湖北电力,2010,34(4):76-78.
作者姓名:曾亮
作者单位:湖北省荆州供电公司,湖北,荆州,434002
摘    要:自从江陵、兴隆两座500 kV变电站接入荆州220 kV主网后,改变了主要依靠220 kV网络输入电力和西电东送的原有模式,逐步形成以两座500 kV变电站下网功率为主,220 kV电网输入电力为辅的新格局,主网的供电能力和运行稳定度大幅提升。

关 键 词:电网  变电站  西电东送

Development and Prospects of Jingzhou Power Grid in Hubei
ZENG Liang.Development and Prospects of Jingzhou Power Grid in Hubei[J].Hubei Electric Power,2010,34(4):76-78.
Authors:ZENG Liang
Affiliation:ZENG Liang(Planning Department,Jingzhou Power Supply Company,Jingzhou Hubei 434002,China)
Abstract:Since the 500 kV Jiangling and Xinglong electric substations are connected in 220 kV main network of Jingzhou,the previous modes of both power input mainly depending on 220 kV network and west-to-east power transmission are changed.The new pattern of power output mainly depending on the two 500 kV electric substations and power input through 220 kV network acting as an auxiliary is gradually formed.So both the power supply capability and operation stability of the main network are widely advanced.
Keywords:power grid  electric substation  west-to-east power transmission