公伯峡水电站2004年底两台机组同时发电可行性分析
引用本文:姚福海,春光魁. 公伯峡水电站2004年底两台机组同时发电可行性分析[J]. 西北水电, 2002, 0(1): 28-29
作者姓名:姚福海  春光魁
作者单位:国家电力公司西北勘测设计研究院,西安,710065
摘    要:总结李家峡水电站发电初期的经验教训,在此基础上,对公伯峡水电站2004年底两台机组同时发电的可行性做了初步分析。其结果表明,只要合理组织,严格管理,并确保2001年6月份厂房开始浇筑混凝土,这个计划是能够实现的。

关 键 词:公伯峡水电站 机组 发电 可行性
文章编号:1006-2610(2002)01-0028-02
修稿时间:2001-06-29

Analysis on feasibility of two Gongboxia units commissioned by 2004
YAO Fu hai , CHUN Guang kui. Analysis on feasibility of two Gongboxia units commissioned by 2004[J]. Northwest Water Power, 2002, 0(1): 28-29
Authors:YAO Fu hai & CHUN Guang kui
Abstract:By drawing on the experience and lessons at the initial generation stage of the Lijiaxia power station, preliminary analysis is conducted on feasibility of two units of the Gongboxia power station commissioned by the end of 2004. The results indicate this schedule can be realized provided that the construction is well organized and strictly controlled and it is ensured to start concreting the powerhouse in June of 2001.
Keywords:surplus water  construction progress  power generation  