冶勒水电站廊道混凝土防渗墙施工技术
引用本文:石峰. 冶勒水电站廊道混凝土防渗墙施工技术[J]. 水力发电, 2004, 30(11): 59-62
作者姓名:石峰
作者单位:中国水利水电基础工程局,天津,武清,301700
摘    要:根据设计要求,冶勒水电站工程右坝体深厚覆盖层防渗墙处理深度需达220m。目前,国内外施工工艺无法达到该深度,设计将防渗墙分为上、下两段,下段防渗墙在廊道内施工,在施工中采用了最先进的成墙设备——双轮铣及改型的低桅杆冲击反循环钻机,取得了良好效果。

关 键 词:坝基防渗  廊道  防渗墙  冶勒水电站
文章编号:0559-9342(2004)11-0059-04

Construction technology of concrete cut-off wall in the gallery of Yele Hydropower Station
Shi Feng. Construction technology of concrete cut-off wall in the gallery of Yele Hydropower Station[J]. Water Power, 2004, 30(11): 59-62
Authors:Shi Feng
Abstract:Base on the design requirements, the cut-off system in the right bank area of Yele hydropower station has to reach 220 m deep. This depth cannot be reached by any reliable construction technologies worldwide presently. Cut-off system has been divided into upper and lower sections. Regarding the lower section, the cut-off wall executed in a tunnel, the latest and advance equipment Bauer Trench Cutter and modified low head percussion drilling rig have been used in this project successfully.
Keywords:dam foundation seepage prevention  gallery  seepage control wall  Yele Hydropower Station