特高压GIL接入对断路器瞬态恢复电压的影响
作者姓名:孙义  刘景晖  郑昕雷  李江涛  徐逸清  史大军
作者单位:中国电力工程顾问集团华东电力设计院有限公司, 上海 200063;西安交通大学电气工程学院, 陕西 西安 710049
基金项目:国家重点研发计划资助项目(2017YFB0902701)
摘    要:特高压气体绝缘金属封闭输电线路(GIL)的接入对断路器瞬态恢复电压(TRV)幅值和瞬态恢复电压上升率(RRRV)均会产生影响,可能危及断路器开断能力。文中基于同塔双回特高压交流架空线-双回GIL混合输电线路,利用EMTP-ATP仿真研究变电站内断路器端部发生三相短路故障时,GIL长度、接入位置与GIL引接站测量设备对断路器TRV幅值和RRRV的影响。仿真结果表明,GIL的接入对断路器TRV幅值和RRRV有较大影响;GIL长度增加对TRV幅值产生较大影响,但对RRRV影响较小;为了限制RRRV,应将GIL安装在架空线中段,且应安装金属氧化物避雷器 (MOV)限制TRV幅值;GIL引接站测量设备对断路器TRV幅值和RRRV影响均较小。文中研究成果可为含GIL的特高压线路中断路器的TRV计算及参数设计提供参考。

关 键 词:特高压气体绝缘金属封闭输电线路(GIL)  断路器  瞬态恢复电压(TRV)  瞬态恢复电压上升率(RRRV)  混合输电线路  EMTP-ATP仿真
收稿时间:2022/3/25 0:00:00
修稿时间:2022/7/3 0:00:00

Influence of UHV GIL access on transient recovery voltage of circuit breaker
Authors:SUN Yi  LIU Jinghui  ZHENG Xinlei  LI Jiangtao  XU Yiqing  SHI Dajun
Affiliation:East China Electric Power Design Institute, CPECC, Shanghai 200063, China;School of Electrical Engineering, Xi''an Jiaotong University, Xi''an 710049, China
Abstract:The access of ultra high voltage (UHV) gas-insulated transmission line (GIL) affects both the transient recovery voltage (TRV) amplitude and the rate of rise of TRV (RRRV) of circuit breakers,which may endanger the breaking capacity of circuit breakers. Based on the double-circuit UHV accurate current (AC) overhead line on the same tower and the double-circuit GIL hybrid transmission line,EMTP-ATP simulation is used to study the influence of GIL length,access position and GIL lead station measurement equipment on the TRV amplitude and RRRV of the circuit breaker when a three-phase short-circuit fault occurs at the end of the circuit breaker in the substation. The simulation results show that the access of the GIL has a greater impact on the TRV amplitude and RRRV of the circuit breaker. The increase in the length of the GIL has a greater impact on the TRV amplitude,but the impact on RRRV is small. In order to limit the RRRV,the GIL should be installed in the middle of the overhead line,and the metal oxide varistor (MOV) should be installed to limit the TRV amplitude. The measurement equipment of the GIL terminal station has little effect on the TRV amplitude and RRRV of the circuit breaker. The research results can provide a reference for the TRV calculation and parameter design of circuit breakers in UHV lines with GIL.
Keywords:ultra high voltage (UHV) gas-insulated transmission line (GIL)  circuit breaker  transient recovery voltage (TRV)  rate of rise of TRV (RRRV)  hybrid transmission line  EMTP-ATP simulation