天安煤矿矿井提升设备能力的核算
引用本文:赵波涛.天安煤矿矿井提升设备能力的核算[J].山西煤炭,2011,31(2):60-62.
作者姓名:赵波涛
作者单位:太原理工大学矿业工程学院,山西,太原,030024;山西省煤炭规划设计院,山西,太原,030045
摘    要:经对天安煤矿矿井提升设备能力的核算后,得出结论:主提升设备SPJ-800型带式输送机1,台能满足矿井能力需求;副斜井提升设备JK-3/2.2型单滚筒提升绞车1台,也能满足运输材料、支架、矸石、人员的要求。

关 键 词:提升设备  提升方式  主斜井  副斜井

Accounting of the Lift Equipment Capacity in Tian'an Mine
ZHAO Bo-tao.Accounting of the Lift Equipment Capacity in Tian'an Mine[J].Shanxi Coal,2011,31(2):60-62.
Authors:ZHAO Bo-tao
Affiliation:ZHAO Bo-tao~(1,2) (1.College of Mining Engineering,Taiyuan University of Technology,Taiyuan Shanxi,030024,2.Shanxi Coal Design Institute,Taiyuan Shanxi 030045)
Abstract:By the accounting of the lift equipment capacity in Tian'an mine,the study concludes that the main lift equipment(one SPJ-800 belt conveyor) can satisfy the mine's demand;the auxiliary inclined shaft lift equipment(one JK-3/2.2 single drum hoist) can also satisfy the transporting demand of materials, support,gangue and personnel.
Keywords:lift equipments  hoist method  main inclined shaft  auxiliary slope hoist  