考虑源荷相关性的独立微电网日前风险调度策略
引用本文:郝福忠,刘 昊,胡誉蓉,贺 翔,魏小钊,孙 毅,王诗玮. 考虑源荷相关性的独立微电网日前风险调度策略[J]. 电力需求侧管理, 2024, 26(3): 34-40
作者姓名:郝福忠  刘 昊  胡誉蓉  贺 翔  魏小钊  孙 毅  王诗玮
作者单位:国网河南省电力公司,郑州 450000;国网河南省电力公司 电力科学研究院,郑州 450052;华北电力大学 电气与电子工程学院,北京 102206
基金项目:国网河南省电力公司科技项目(52170222000V)
摘    要:随着微电网内分布式可再生能源的渗透率提升,灵活资源调度不足导致的弃光和失负荷会对微电网运行造成较大的影响。通过充分调度各类分布式灵活资源,提出一种计及源荷相关性的微电网日前风险调度策略。在考虑灵活资源的独立微电网调控架构下,采用考虑相关性的拉丁超立方抽样方法处理分布式光伏及负荷的不确定性,分析相关性影响下的微电网期望调度成本、弃光与失负荷损失成本及条件风险成本,构建总调度成本期望值最小的日前优化调度模型。仿真结果表明,所提策略通过合理调度灵活资源及预留备用容量,能够有效平衡微电网运行经济性及运行风险。

关 键 词:独立微电网;日前风险调度;相关性;条件风险价值
收稿时间:2024-02-01
修稿时间:2024-03-09

Day-ahead risk scheduling strategy of independent microgrid considering source-load correlation
HAO Fuzhong,LIU Hao,HU Yurong,HE Xiang,WEI Xiaozhao,SUN Yi,WANG Shiwei. Day-ahead risk scheduling strategy of independent microgrid considering source-load correlation[J]. Power Demand Side Management, 2024, 26(3): 34-40
Authors:HAO Fuzhong  LIU Hao  HU Yurong  HE Xiang  WEI Xiaozhao  SUN Yi  WANG Shiwei
Affiliation:State Grid Henan Electric Power Company,Zhengzhou 450000,China;Electric Power Science Research Institute State Grid Henan Electric Power Company,Zhengzhou 450052,China;Electrical and Electronic Engineering College,North China Electric Power University,Beijing 102206,China
Abstract:As the penetration rate of distributed renewable energy within microgrids increases,insufficient flexible resource scheduling leading to curtailment and loss of load will have a significant impact on the operation of microgrids. A microgrid day ahead risk scheduling strategy that takes into account source load correlation by fully scheduling various distributed flexible resources is proposed. Under the independent microgrid regulation architecture considering flexible resources,the Latin hypercube sampling method considering correlation is adopted to deal with the uncertainty of distributed photovoltaics and loads. The expected scheduling cost,loss cost of abandoned light and load,and conditional risk cost of microgrids under the influence of correlation are analyzed,and a day-ahead optimization scheduling model with the minimum expected total scheduling cost is constructed. The simulation results show that the proposed strategy can effectively balance the economic and operational risks of microgrid operation by reasonably scheduling flexible resources and reserving reserve capacity.
Keywords:independent microgrid;day-ahead risk scheduling;correlation;conditional value at risk