9E HRSG高压汽包上抬关联部件应力分析及监测
引用本文:许志贵,严桂生.9E HRSG高压汽包上抬关联部件应力分析及监测[J].锅炉技术,2010,41(1).
作者姓名:许志贵  严桂生
作者单位:杭州锅炉集团股份有限公司,浙江,杭州,310004
摘    要:某热电厂早期进口的9E HRSG高压汽包上抬过程中,汽包或与汽包相连的部件可能产生过大的变形和应力。为评估抬升过程的安全性,采用有限元软件对汽包及关联部件进行应力应变分析,并对抬升过程进行动态监测。结果表明此次抬升对汽包、相关管道和锅炉今后的运行无影响。

关 键 词:HRSG  汽包  应力分析  应力监测  有限元  

Stress Analysis and Monitoring to High Pressure Steam Drum and Associated Pipes in the Process of Being Lifted
XU Zhi-gui,YAN Gui-sheng.Stress Analysis and Monitoring to High Pressure Steam Drum and Associated Pipes in the Process of Being Lifted[J].Boiler Technology,2010,41(1).
Authors:XU Zhi-gui  YAN Gui-sheng
Affiliation:HangZhou Boiler Group Co.Ltd.;Hangzhou 310004;China
Abstract:In the process of lifting the high pressure steam drum of a 9E HRSG,great deformation and stress may happened to the drum and associated pipes.In order to evaluate the process,FEA method is used to analyse the stress of the drum and associated pipes,and monitors the dynamic stress of the process.The result shows that,the lifting process has no influence for the operation of this boiler in the future.
Keywords:HRSG  steam drum  stress analysis  stress monitoring  FEA  